Construction Build Schedule Template

By Infinity Lending ServicesUpdated March 4, 20267 min read

Quick Answer

A typical residential new build takes 6-12 months from groundbreaking to completion. The schedule is divided into phases: site work, foundation, framing, mechanical rough-in, interior finishes, and final completion. Weather, permits, and material availability are the most common schedule risks.

Phase 1: Pre-Construction (2-4 weeks before start)

  • Permits obtained
  • Site surveyed and staked
  • Utility locates completed
  • Materials ordered (long-lead items)
  • Subcontractors confirmed and scheduled
  • Temporary utilities installed (power, water)
  • Portable facilities delivered

Phase 2: Site Work and Foundation (3-4 weeks)

Task Duration Notes
Clearing and grading 3-5 days Remove trees, level site
Excavation 2-3 days Dig for foundation
Footings 2-3 days Form, pour, cure
Foundation walls 3-5 days Form, pour, cure, waterproof
Backfill and compaction 1-2 days After waterproofing
Underground plumbing 2-3 days Below slab or crawl space
Slab pour (if applicable) 1-2 days Cure time needed
Foundation inspection 1 day Required before framing

Phase 3: Framing (3-4 weeks)

Task Duration Notes
Floor system 3-5 days Joists, subfloor
Wall framing 5-7 days Exterior and interior walls
Roof trusses/rafters 3-5 days Set and brace
Sheathing 3-5 days Walls and roof deck
Windows and exterior doors 2-3 days Install in framed openings
House wrap 1-2 days Weather barrier
Framing inspection 1 day Required before covering

Phase 4: Mechanical Rough-In (2-3 weeks)

Task Duration Notes
Plumbing rough-in 4-5 days Supply and drain lines
Electrical rough-in 4-5 days Wiring, panels, boxes
HVAC rough-in 3-4 days Ductwork, unit placement
Low-voltage wiring 1-2 days Data, security, audio
Mechanical inspections 1-2 days Each trade inspected

Phase 5: Insulation and Drywall (2-3 weeks)

Task Duration Notes
Insulation 2-3 days Walls, ceilings, floors
Insulation inspection 1 day Required before drywall
Drywall hanging 3-5 days All interior surfaces
Drywall taping/finishing 5-7 days Multiple coats, sanding

Phase 6: Interior Finishes (4-6 weeks)

Task Duration Notes
Interior paint 5-7 days Primer and two coats
Cabinets 3-5 days Kitchen and bathrooms
Countertops 2-3 days Template and install
Flooring 5-7 days Tile, hardwood, LVP, carpet
Trim and doors 4-5 days Baseboards, casings, doors
Fixtures 3-4 days Lighting, plumbing, hardware
Appliances 1-2 days Delivery and install

Phase 7: Exterior Finishes (2-3 weeks, concurrent with interior)

Task Duration Notes
Roofing 3-5 days Shingles, flashing, gutters
Siding/exterior finish 5-7 days Siding, brick, stone
Exterior paint/stain 3-5 days If applicable
Driveway 2-3 days Concrete or asphalt
Landscaping 3-5 days Grading, sod, plants

Phase 8: Final Completion (1-2 weeks)

Task Duration Notes
Punch list 3-5 days Address all deficiencies
Final cleaning 1-2 days Construction clean and detail
Final inspections 1-2 days Building, mechanical, fire
Certificate of occupancy 1-3 days Issued after final inspection
Professional photography 1 day For listing

Key Takeaways

  • ✓Plan for 6-12 months for a typical residential build
  • ✓Schedule around inspection requirements and lead times
  • ✓Weather and material availability are the biggest risks
  • ✓Buffer time prevents schedule pressure from causing mistakes

Frequently Asked Questions

About the Author

Written by the nuFLIP lending team — America's Residential Transition Loan (RTL) Experts. nuFLIP helps real estate investors finance Fix & Flip, Bridge, Ground-Up Construction, and DSCR rental loans with fast underwriting, ARV-based loan sizing, rehab funding, and institutional capital solutions.

Ready to Finance Your Next Deal?

Get instant, transparent loan quotes with exact rates and terms. No surprises, no obligation.

Related Articles

Construction Financing

Builder's Risk Insurance for Construction Projects

Everything you need to know about builder's risk insurance for new construction and renovation projects, including coverage, costs, and requirements.

Construction Financing

Construction Loan Draw Process: Step-by-Step Guide

A complete guide to the construction loan draw process, from requesting funds to inspection and disbursement.

Construction Financing

Construction Permit Timeline: What to Expect

Understand the construction permit process, typical timelines, and how to avoid delays that can stall your building project.