Schedule of Values for Construction Loans

By Infinity Lending ServicesUpdated March 4, 20266 min read

Quick Answer

A schedule of values (SOV) breaks the total construction budget into line items with assigned dollar values. Each draw request references the SOV to show what percentage of each line item is complete and how much funding is being requested.

What Is a Schedule of Values?

A schedule of values (SOV) is a detailed cost breakdown that assigns a dollar value to every component of a construction project. It serves as the blueprint for how construction loan funds are disbursed through draws.

The SOV is submitted to the lender before construction begins and becomes the basis for all future draw requests.

How It Works

Creating the SOV

The builder breaks the total construction budget into individual line items:

Line Item Budget % of Total
Site work $30,000 8%
Foundation $35,000 9%
Framing $65,000 17%
Roofing $18,000 5%
Exterior finishes $25,000 7%
Plumbing $22,000 6%
Electrical $20,000 5%
HVAC $18,000 5%
Insulation/drywall $20,000 5%
Interior finishes $75,000 20%
Landscaping $12,000 3%
Contingency $40,000 10%
Total $380,000 100%

Draw Requests Against the SOV

When requesting a draw, the builder reports the completion percentage for each line item:

Line Item Budget % Complete Amount Requested
Site work $30,000 100% $30,000
Foundation $35,000 100% $35,000
Framing $65,000 50% $32,500
All others — 0% $0
Draw Total $97,500

Inspection and Approval

After submitting a draw request, the lender sends an inspector to verify that the reported completion percentages are accurate. Once verified, the draw is approved and funds are released.

Best Practices

  • Be detailed: More line items provide better tracking and smoother draws
  • Be accurate: Inflated values for early items create problems in later draws
  • Front-load appropriately: Site work and foundation are naturally front-loaded
  • Include contingency: Show it as a separate line item
  • Match your contract: The SOV should align with your contractor agreement
  • Plan for retainage: Some lenders hold 5-10% until project completion

Key Takeaways

  • ✓The SOV is the foundation of the draw process
  • ✓Each line item has a specific dollar value
  • ✓Draw requests reference completion percentages against the SOV
  • ✓Accurate SOV creation prevents draw delays

Frequently Asked Questions

About the Author

Written by the nuFLIP lending team — America's Residential Transition Loan (RTL) Experts. nuFLIP helps real estate investors finance Fix & Flip, Bridge, Ground-Up Construction, and DSCR rental loans with fast underwriting, ARV-based loan sizing, rehab funding, and institutional capital solutions.

Ready to Finance Your Next Deal?

Get instant, transparent loan quotes with exact rates and terms. No surprises, no obligation.

Related Articles

Construction Financing

Managing Change Orders on Construction Projects

Learn how to manage change orders on new construction projects, control costs, and maintain lender compliance.

Construction Financing

Construction Contingency Budget: How Much Is Enough?

Learn how to set the right contingency budget for your construction project and what expenses it should cover.

Construction Financing

Preventing Construction Cost Overruns

Learn the most common causes of construction cost overruns and proven strategies to keep your building project on budget.